Tuesday, April 28, 2009

Progress on south and north side renovations

Placement of steel for the support columns on the south side of the library is moving forward now that water suppression is under control. Steel was delivered today and the poles are being placed in their proper locations. Soon masonry work will begin and you will start to see the new footprint of the coffee shop and teen room emerge.

On the north side of the building demo work continues in the elevator pit and water suppression will start to be addressed this week. T. J. Roofing will be on site soon to open up the library's roof to make room for the new elevator once the demo work is completed by Kreighoff-Lenawee .

Thursday, April 16, 2009

Monumental Day at the Library

Heavy construction is now taking place on all four sides of the library as of today (April 16, 2009). The insulation (EFIS) covering all four sides of the building is being removed to address the water issues the library is facing. It will be replaced by 8 feet of brick along the base of the building's north, east and west walls. Above the brick on these walls will be placement of new EFIS to water proof the building. The front of the building on Maumee is being removed to make room for the new facade which will feature brick and stone from the sidewalk to the concrete cap above the front doors.



The new elevator arrived today and it was pretty amazing to watch that being delivered. Our current elevator will be down for about two months during the elevator replacement. Please pardon the equipment located on the main floor of the library as work is taking place to remove the old elevator and prepare for the installation of the new elevator. If you need assistance to access materials located on the youth floor please let any employee know and we would be pleased to assist you.

Wednesday, March 18, 2009

Moving Forward with New Design Plans

On Monday, March 16 the City Commission approved our new design plans to replace the facade on all four sides of the library. The facade is being replaced due to ongoing water issues the library has been facing. The new design was created by architect Todd Seidell to compliment the other buildings in the city complex on Maumee Street. Construction will take place by early April.

Tuesday, February 10, 2009

Renovation Update

We are moving forward with our renovation as you can see from the truck out front. The City's DPW (Department of Public Works) will be here for a week or so doing demo work in the south mezzanine area. They are preparing that area for renovation by knocking down the walls in the mezzanine area on the south side of the building. DPW is sending the debris from the demo work down a chute from the mezzanine to a truck out front. This area will become a new casual use area for the library. Library visitors will be welcome to sit in this area to read or study and encouraged to bring their laptops to use with the library's public wireless network.

Tuesday, November 11, 2008

Elevator Upgrade Coming Soon

The elevator which services the library's meeting room and youth area will be upgraded starting in November. It will be replaced by Otis Elevator and will be unavailable for use during the upgrade. It is expected to be out of service for at least a month. We apologize for the inconvenience this will cause. Please contact a staff member if you need assistance and we will be pleased to help you.

Saturday, August 2, 2008

Library Closed August 4 - 9 for Renovation

The Adrian Public Library will be closed for electrical renovations from Sunday August 3 - Sunday August 10. We expect to reopen on Monday August 11 at 10 a.m. Library materials can be returned to the book drop on the north side of the library during our renovation. During our closure library patrons can access their library records, renew materials, place holds and use our electronic research databases by visiting our web page www.adrian.lib.mi.us . Clegg Electric will be updating the library's electrical service in the building and working with Consumers Energy to implement the electrical framework for the new City Hall complex during our closure.

Sunday, July 20, 2008

Electrical Update and Impact on Library Square

Library visitors over the last few weeks have seen a transformation in Library Square, the park to the north of the library, from construction zone back to the park's natural beautiful state. A significant amount of work took place to open up the ground in Library Square to place the electrical framework for the new city complex. Most of the digging has now been completed and the grass has been seeded in selected areas. Further work on the grass areas will take place this fall by the City's Park and Forestry Department. For now, the electrical work has moved into the library and library patrons can expect to hear the sounds of progress from our electrical crew during your library visits. Our electrical crew is doing their best to keep the noise down and minimize the impact on library services when possible. However, it has been determined that the Library will have to close for approximately a week when the library switches over to their new electrical service in early August. The exact closure dates are still to be determined and will be shared with the public shortly.